Progress Report - Friday, May 12, 2000 Meritor Automotive
Detroit Industrial Plant and Technology Center Below is a brief summation
covering the important categories relating to the development of the Meritor
Industrial and Technology Center. The intent is not to provide an exhaustive
review of the week's activities, but a brief synopsis. If a more detailed
analysis is required, do not hesitate to call or e-mail. Reports will
be updated biweekly.
|
||||||||||||
The consultant will complete
the four (4) week investigation today. Visual observances and preliminary
testing have indicated a few unexpected problems. A Baseline Environmental
Assessment (BEA) will be required, as expected. Testing did, however,
reveal an underground storage tank on the library property. In addition,
asbestos was identified around pipes in the library and in the stucco
walls.
The consultant walked through the Fisher Guide Building Monday, May 8 with the demolition contractors so that they might refine their bids. Quantities of asbestos will be provided to the contractors no later than Wednesday of next week. Lead paint within the building will not have to be removed prior to top demolition. This will result in a savings from the original development budget. There may, however, be a small increase in landfill cost. Since the materials will contain lead, however, the net effect will be a substantial savings. |
||||||||||||
Municipal Entitlements
|
||||||||||||
On
April 20, two requests were delivered to the City. The first was a request
to appear before council for the purpose of introducing them to the project.
The second was a petition to vacate Radamacher, Rankin, and the alley
behind the library. In addition, we requested the city sell us the lot
on the corner of Radamacher and Fort required for our development, and
sell us two lots on the north side of Fort, required as part of the property
swap with the church.
The requests were forwarded to the City Planning and Development department and the City Department of Public Works for comment. I have talked with both departments requesting they expedite the review. Planning and Development has agreed to make this a priority. DPW has a backlog and has not agreed to move the review process along in an expedited fashion. I am meeting the DPW official today. |
||||||||||||
|
||||||||||||
On Monday, May
8 specifications and the preliminary site plan for the industrial facility
were forwarded to seven potential contractors. Proposals are due back on
May 26. We expect to narrow the field and meet two of the contractors the
following week and make a selection by June 2. |
||||||||||||
|
||||||||||||
The specifications
for the industrial facility were completed on Monday, May 8. No work has
been done on the office. The design of the industrial plant will begin in
earnest after a contractor has been selected. The contractor will be responsible
for design. |
||||||||||||
|
||||||||||||
Until a contractor is selected work has not begun in this area. | ||||||||||||
|
||||||||||||
The original three
demolition bidders was narrowed to two. Both met with the environmental
consultant and walked the site. Bids should be received by the end of next
week (May 19). |
||||||||||||
|
||||||||||||
Nothing to report at this time . |